TransCanada (with Cianbro/Three Phase Construction)

DSC00355SGC provided electrical engineering and survey support for the Kibby Wind Power Project. This project is located north of Eustis, Maine and consists of 44 Vestas V-90 3.0 MW turbines. SGC’s electrical engineering and design effort on this project included the very challenging 34.5 kV electric collector system, a 34.5 kV to 115 kV substation, and a 115 kV underground transmission line. SGC performed survey work in conjunction with collector design, the substation construction and the underground transmission line. Performed field verification of As-Built right-of-way, structure guy locations, line clearing and staking.

Kibby Wind Project