Record Hill LLC, Independence Wind LLCRecord Hill - Turbine in the Fall

SGC performed a preliminary feasibility analysis, project assessment, and electrical engineering services for this 50 MW wind project utilizing 22 Siemens 2.3 MW turbines. SGC developed a preliminary one-line diagram for the collector substation based on the one line utilized in the System Impact Study. This one-line diagram was to be the basis for developing the preliminary substation layout of breakers, switches, and all other major devices used in the design. SGC also developed a preliminary plan view, permit level design for portions of the collector system which formed the basis for submitting a DEP application for a site location permit.

SGC completed the construction design of the 34.5 collector system, combining both overhead and underground design elements.  SGC provided engineering support during the construction phase

Record Hill Wind Project